Cape Town is approving data centres. But its rules still treat them like warehouses

Water and electricity shortages affect some residents, while data centers set up operations in Cape Town

Reportagem
9 de setembro de 2026
14:16
Não deixe a Publica sumir
Nos adicione como fonte preferencial no Google.
Ncediwe Vanqa em uma das sete viagens diárias para buscar água na Cidade do Cabo (África do Sul)
David Harrison/The Continent
Idioma English

This story was made possible with support from the Pulitzer Center and forms part of the Africa leg of Big Tech’s Invisible Hand, a cross-border collaborative investigation led by Brazilian news organisation Agência Pública and the Centro Latinoamericano de Investigación Periodística (CLIP).

For 66-year-old Ncediwe Vanqa, water comes one trip at a time. She walks from her 18m² dwelling in Barcelona, an informal settlement in Gugulethu, Cape Town, to a communal tap as many as seven times a day. She uses a communal pit latrine and, in emergencies, a bucket. To save electricity, she bakes bread using a paraffin heater and uses its heat to warm her home.

Yet across the freeway, less than two kilometres away, the city of Cape Town has opened the planning door to infrastructure operating at an entirely different scale. In July, the City’s Municipal Planning Tribunal approved a planning application by King Air Industria, a multi-billion-rand industrial and logistics park, for two proposed data centres that planning documents identify as intended for Equinix, a US multinational.

Equinix, one of the world’s largest data-centre operators and a key infrastructure provider for hyperscalers such as Amazon, Microsoft and Google, disputes that characterisation.

Its expansion in Cape Town is the focus of this story, part of Big Tech’s Invisible Hand, a cross-border investigation examining how global technology companies are influencing the rules, policies and public infrastructure.

The company told The Continent it “has not submitted any planning or development applications for a data centre in Cape Town” and that “there are currently no development applications under consideration for the site”.

But the city’s own account shows that Equinix met officials at least three times to discuss its data-centre plans. Dozens of planning documents also link the King Air land-use application to Equinix’s proposed development of the site.

At the centre of the King Air dispute is the question of how much water and electricity the proposed Equinix hyperscale data centres will require. Hyperscale data centres are notorious worldwide for consuming inordinate amounts of water and/or electricity to cool the machines.

In its appeal against the building of one of these in Cape Town, the Legal Resources Centre (LRC), a public-interest law organisation, estimated that, if conventional evaporative cooling were used, the two data centres could consume about 4.4 billion litres of water a year. That is almost 11-million litres a day, roughly equivalent to the daily water use of 68,500 Cape Town residents, based on the city’s average consumption benchmark. For a city that narrowly avoided “Day Zero” during the 2018 drought, the potential demand is significant. Equinix did not respond to questions relating to the proposed data centre resources. However, in its papers, King Air told the Tribunal that the final amounts of resource usage would be made available in the site development planning phase.

In the US, data-centre expansion is facing growing community resistance. According to Data & Society, an independent nonprofit research and policy institute in the US, global data-centre energy consumption has grown 12% in five years and could double by 2030. Water use is also rising. The organisation says consumption by Meta, Apple, Microsoft and Google has increased 60% since 2020. As data centres expand into communities, the organisation argues that where they are built has become an increasingly political decision, with consequences for local economies, health, water and energy supplies.

According to the documents before the Municipal Planning Tribunal, the proposed system could need about 174MVA. “If operated continuously near this level,” throughout the year, the data centres could consume roughly 1.4 to 1.5 billion kWh of electricity annually, explained Dr Chantelle van Staden, a senior lecturer at the Stellenbosch University’s Department of Electrical and Electronic Engineering. “This could amount to the annual electricity use of a quarter of a million average Cape Town households,” said Van Staden.

That lack of information troubled at least one member of the tribunal when it considered the land-use approval in July. “Most of us here today actually do not know what is required in respect of water and electricity demand for a facility that we are asked to approve, as no details thereof have been made available,” Municipal Planning Tribunal panel member Wally Johnstone said at a 14 July 2026 meeting. Johnstone was the only one of five panel members opposing the approval of land use for data centres.

The city disputes that the development was approved without adequate consideration and that its energy department had concluded that there would be sufficient supply. The tribunal papers also revealed that Equinix has already paid ‘shared network charges for 160MVA’ of capacity amounting to R33 million. The city said some technical details would be assessed later.

The people on the other side of the grid

Weeks before the tribunal approved the King Air application, Public Protector Kholeka Gcaleka released findings concerning municipal service delivery to informal settlements  Langa and Khayelitsha, which are in close proximity to Equinix’s proposed data centres.

Khayelitsha and Langa are both high-density, mostly poor townships less than 10 kilometres away from the proposed site. In June, after a four-year-long investigation, the public protector found that Cape Town had failed to provide adequate basic services to residents of the two townships, including water, sanitation and electricity. The failures were serious enough to amount to “maladministration” and “prejudice”.

The city told the investigation that budget constraints, infrastructure backlogs and competing service-delivery demands had prevented it from fixing some of these problems. The public protector acknowledged the financial pressures but found they did not absolve the City of its constitutional obligations, with systemic service-delivery failures continuing despite some improvements. 

For residents and Housing Assembly members such as Vanqa, the argument is about who gets scarce resources. The LRC told the tribunal that their objection originates from “a context of acute and overlapping resource constraints in the City of Cape Town where land, water and energy systems are already under significant pressure”.

Hyperscale not a warehouse

South Africa is not new to data centres. Data Centre Map, an industry directory, lists about 64 operating data centres in South Africa and another 10 planned. But hyperscale facilities bring infrastructure demands of a different order, with electricity requirements that can run into hundreds of megawatts. The regulations have not kept pace. South Africa has no dedicated national data-centre policy, while Cape Town has no separate land-use category for hyperscale facilities. The city said data centres are “typically grouped under commercial/industrial users,” the city told The Continent. They are assessed under existing industrial or warehousing rules.

Johnstone called this “wholly inadequate” and added that it was “simplistic to consider a data centre as a warehouse that only stores computer systems.” The LRC went further, describing the classification as “patently incorrect and possibly misleading”.

Speaking on how the application before the tribunal uses legislation that classifies data centres as warehouses, Grant Oosterwyk, a senior lecturer in information systems at the University of Cape Town who previously worked at a small-scale data centre, said the current approach creates an artificial blind spot.

“This allows these facilities to avoid the rigorous, baseline industrial impact assessments that a facility of this scale would normally trigger under a modern planning framework,” Oosterwyk said.

“Treating a 100MW facility with industrial-scale cooling, heavy diesel backup, and continuous heavy vehicle movement as a simple storage warehouse is a profound regulatory mismatch. The category has simply not caught up with the infrastructure being built inside it.”

What Cape Town won’t disclose about its data-centre pipeline

The proposed Equinix development is also not the only hyperscale project being contemplated in Cape Town. Brett Herron, a member of the Western Cape Provincial Parliament, told The Continent that Cape Town is “courting” four hyperscale projects.

He identified Equinix’s proposed King Air facilities, Teraco’s planned 60MW expansion and Cavaleros Group’s announced 360MW Cosmas Data Cities project. Herron calculates their potential combined demand at approximately 580MW. Based on publicly available information, he calculates that if all the projects were built at the stated capacities, their combined demand would equal roughly 35% of Cape Town’s current peak electricity demand. 

Deputy mayor Alderman Eddie Andrews said Cape Town has approved five data centres and has another two under assessment. But the city would not name the companies behind those projects, citing the Privacy of Personal Information Act (POPIA). However, it did not explain under which provisions of the act prevented it from disclosing electricity-load information or why project-level demand could not be released.

Aside from legislation, the city’s Lance Greyling, the City’s Director of Economic Development and Investment, confirmed that he met Equinix three times between July 2025 and June 2026, all at the company’s request. 

At the first meeting in July 2025, Greyling said, Equinix told him of “their intention to invest in data centres in Cape Town”. Four months later, Greyling, mayoral committee member James Vos, city officials and Western Cape government representatives met the company after it had bought land at King Air Industria. Greyling said Equinix discussed “their intentions in relation to the way forward for the proposed business”. At a third meeting in June, the company provided a further update on its planned data-centre investment.

Greyling said, “I have met Equinix before at their request but have at no stage held discussions on statutory approvals.” Yet there were no agendas or minutes kept. He said his role is to engage potential investors and promote Cape Town as a place for economic growth, provided they meet the necessary legal requirements.

In South Africa, meetings between officials and private investors are not routinely disclosed or regulated. There is no evidence Equinix influenced the statutory approval process, but the company met Cape Town’s investment-promotion office repeatedly as its data-centre plans developed. With no minutes kept, there is no detailed public record of what was discussed.

The Continent interviewed two city councillors who said the implications of data-centre expansion had not been widely debated in the city council. Khalid Sayed, the ANC’s leader in the Western Cape, told The Continent that data centres, including their water and electricity demands, have barely featured in political forums. He said this may reflect both a lack of understanding and oversight failure.

Not just Cape Town

Cape Town is not alone. eThekwini Municipality acknowledged that its planning scheme has no specific definition for hyperscale or AI data centres and said it was still considering how to regulate their infrastructure demands.

Yet the municipality in April said that its full council had authorised the city to enter into an agreement with the Korean South Power Consortium to explore a proposed AI data centre on municipal land in the south of Durban. Council documents estimate the development could cost between $3 billion and $10 billion and state that the municipality would provide the land and infrastructure required for the project. The city said the project’s water and electricity requirements have not yet been determined.

Marketing and communications director Mandla Nsele said the issues raised regarding data centre demands “are the subject of internal discussions,” meaning the municipality is unable to provide detailed data. 

One of the council members against the development, Andre Beetge, said a council report regarding the project does not “adequately address the energy demand trajectory associated with AI data centres – projected to escalate dramatically over the next few years.”

David Harrison/The Continent
David Harrison/The Continent

Não é todo mundo que chega até aqui não! Você faz parte do grupo mais fiel da Pública, que costuma vir com a gente até a última palavra do texto. Mas sabia que menos de 1% de nossos leitores apoiam nosso trabalho financeiramente? Estes são Aliados da Pública, que são muito bem recompensados pela ajuda que eles dão. São descontos em livros, streaming de graça, participação nas nossas newsletters e contato direto com a redação em troca de um apoio que custa menos de R$ 1 por dia.

Clica aqui pra saber mais!

Se você chegou até aqui é porque realmente valoriza nosso jornalismo. Conheça e apoie o Programa dos Aliados, onde se reúnem os leitores mais fiéis da Pública, fundamentais para a gente continuar existindo e fazendo o jornalismo valente que você conhece. Se preferir, envie um pix de qualquer valor para contato@apublica.org.

Vale a pena ouvir

EP 232 A violência como promessa em ano eleitoral – com Bruno Paes Manso

Jornalista e pesquisador fala sobre o avanço do discurso de violência e seus efeitos no Brasil

0:00

Leia de graça, retribua com uma doação

Na Pública, somos livres para investigar e denunciar o que outros não ousam, porque não somos bancados por anunciantes ou acionistas ricos.

É por isso que seu apoio é essencial. Com ele, podemos continuar enfrentando poderosos e defendendo os direitos humanos. Escolha como contribuir e seja parte dessa mudança.

Junte-se agora a essa luta!

Newsletter

Saiba de tudo que investigamos

Assinar
Fique por dentro

Receba conteúdos exclusivos da Pública de graça no seu email.

Assinar

Artigos mais recentes

Congresso travou regulação de câmeras corporais enquanto letalidade policial batia recorde

|

Câmeras corporais de policiais se tornaram campo de disputa política que vai muito além da responsabilização por abusos

Prevenção a violências contra crianças passa batida em propostas de presidenciáveis

|

Maior parte dos programas ignora prevenção a mortes ou violência sexual de crianças e sequer menciona primeira infância

Lula e Flávio, mais cautelosos que o usual, deixam público dar recados no 7 de setembro

|

Em SP, ato da direita levou menos gente às ruas que no ano passado; em BSB, Lula seguiu protocolo “seguro”

André Mendonça mobiliza orações e se torna ícone do 7 de setembro bolsonarista

|

Crise no STF se torna “guerra santa” entre evangélicos e coloca o ministro como “mártir” em oposição a Moraes

Contando com memória curta do eleitor, candidatos antes cassados voltam às urnas em 2026

|

Políticos cassados no passado tentam reconquistar votos beneficiados por leis, decisões da Justiça ou até pelo tempo

Crise no STF após divulgação de conversas entre Moraes e Vorcaro: como chegamos até aqui?

|

André Mendonça escancara divisões na Corte ao tirar sigilo de investigação citando colega e tema deve impactar eleições

Resgates de pessoas em condição de escravidão caem no Brasil, mas disparam em SP, diz CPT

|

Em 6 meses de 2026, o estado teve mais pessoas resgatadas em condições análogas à escravidão que em todo o ano passado

Fiesp defende modelo inconstitucional de Bukele na segurança e afaga candidatos da direita

|

Candidato ao governo do Paraná, Sergio Moro promete presídio “El Salvador” durante abertura de evento em São Paulo

Mansões, carros de luxo, viagens: a vida de Eduardo Bolsonaro e Figueiredo nos EUA

|

Levantamento revela que ex-deputado e influenciador mantêm vida de alto padrão nos EUA